"Can we prevent disruption? No, we're tearing up streets," Fort Myers Mayor Kevin Anderson told Florida Weekly this fall, talking about the Midtown work that is now underway. He was speaking in plain terms. Two blocks apart, the city is digging up roads to reach old pipes and a demolition crew is finishing off the old Red Sox spring training stadium. Nothing new is going up on either site yet. The order is intentional. Midtown is being rebuilt from the ground up, starting below the pavement, and the city expects buildings to follow once the groundwork is finished.
Phase 1 is mostly below the pavement
In late October the City of Fort Myers announced that Phase 1 of the Midtown Improvement Project had begun. The area runs from Dr. Martin Luther King Jr. Boulevard to Broadway Avenue to Hoople Street to Central Avenue. That is about one-third of Midtown's 243-acre redevelopment area, which stretches south to Edison Avenue, west to U.S. 41, and east to Fowler Street.
The price is nearly $29.5 million. The city lists the work in rough order of depth: water and sewer lines first, then drainage and stormwater, then road rebuilding, sidewalks, streetlights, trees, benches, and signs. The city's Midtown FAQ gives the reason directly. Many of the area's utilities and much of its public infrastructure are aging and need replacement. The FAQ ties the project to getting "Midtown for future growth and redevelopment" ready.
City Council approved the contract on March 16, 2026. It set a guaranteed maximum price of $29,485,399.99 with AIM Construction Contracting. At that point, Gulfshore Business reported that construction was expected to start in May. Work actually began in the fall. The city now expects it to last through late 2027.
What the work looks like from your driveway or office
Phase 1 includes places a lot of Fort Myers residents already go. Gulfshore Business counts Collaboratory, the Rosa Parks Transportation Center and Greyhound station, Fire Station 11, and the Joseph P. D'Alessandro Office Complex among Midtown's civic and transit anchors. Most of the work is replacing utilities, so the disruptions come from that kind of construction. Here is what the city and its FAQ say to expect:
- Daytime lane closures and equipment in the work zones, with barricades meant to keep sidewalks next to businesses open.
- Water shutoffs with written notice ahead of time. Affected properties also get a boil-water notice, and the city sends a rescission notice once testing confirms the water is safe.
- Driveway crossings announced in advance, so you have time to move your car before crews cut across for new utilities, sidewalks, or resurfacing.
- Mail and trash changes when construction blocks safe access, with temporary arrangements worked out with USPS.
- Dust control with silt fencing and water trucks. Noise will change day to day depending on whether crews are digging out pipe, replacing road surface, or installing streetscape.
Detours and closures are announced through the project's email updates. You sign up through the public information team at [email protected], which sends out the current work schedule and anything that may affect your route. The mayor told Florida Weekly that a maintenance-of-traffic plan will keep cars moving around active work zones. He said the payoff is worth it because many Midtown streets "need a lot of love."
The street you get back is wider
Once the pipes are in, the surface work comes next, and it is a big change for Midtown. According to the FAQ, the new walks will be 7.5 to 12 feet wide, with tree and landscape areas, benches, bike racks, trash cans, and streetlights. Along Edison Avenue and Jackson Street, the plan calls for a shared-use trail that ties Midtown into the city's wider bicycle and pedestrian network.
Jackson Street is where Collaboratory sits, at 2031 Jackson St. The nonprofit hosted the city's public information meeting on the project on September 17. Its president and CEO, Dawn Belamarich, told Florida Weekly that a revitalized district could "increase visibility, accessibility and engagement by attracting more people, businesses and organizations to the area." She also said redevelopment should consider "the needs of existing businesses and nonprofits that have helped shape Midtown's identity."
The stadium site is clearing faster than its future is being decided
A few blocks over, the change is far more visible. City of Palms Park cost $51.5 million when it was built in the early 1990s. Honc Destruction Inc. began taking it down on June 1, 2026, under a contract worth just under $1 million. Florida Weekly reported the demolition nearly finished, and the contract calls for completion by the end of November.
What replaces the stadium is still a proposal, and it has moved through four steps since September:
- September 16. Card & Associates, the city's private developer partner, asked City Council to pick from four indoor fieldhouse options ranging from 162,000 to 200,000 square feet. Council members agreed to focus on the largest one for now. No official vote was taken, Gulfshore Business reported.
- The economic study. Points Consulting, commissioned by Card and the city as part of a $356,180 site scoping process, estimated the fieldhouse could generate $62.7 million a year in economic impact once it is fully running. Card's own bar for success is $20 million or more.
- October 23. RC Peacock Consulting Group held an open house on the concept. Gulf Coast News reported plans for youth and travel sports such as football, soccer, and volleyball, plus concerts. Cole Peacock said the facility could also include hotels and parks. The total cost has not been set, and City Council has to approve the project before construction can begin.
- Next. Card has agreed to cover development costs, including paying the city back for site scoping, if a formal construction agreement is reached. Gulfshore Business reported that agreement could still be months away.
The conceptual site plan puts the fieldhouse near the Fort Myers Skatium, the city-run rink on Broadway. It surrounds the fieldhouse with apartments, townhouses, hotels, retail, and dining. Parking is one of the hardest problems to solve, because each larger fieldhouse option leaves less room around it.
Why the private projects are waiting on the pipes
Asked what comes next for the stadium site, the mayor said the infrastructure comes first:
"It's still up in the air at the moment, but what we're hoping is that as the infrastructure gets done and these other entities start showing interest in Midtown, you're going to see other people show interest as well, other developers."
Anderson made that comment to Florida Weekly. He said he hopes to see "a lot of multifamily residential, a lot of commercial space, retail, more retail than commercial, but you know, restaurants, bars, everything that supports people who live in a community."
Some private projects are already further along. The mayor describes Montage at Midtown, Catalyst Community Development's 321-unit apartment building at 2325 Victoria Avenue, as already completed. Ground was broken September 22, 2026, on a new city police headquarters. The mayor expects it to be finished in late 2028.
The former News-Press site shows what happens when the problem is in the ground itself. The News-Press reported on July 27 that Midtown Catalyst, which holds the city contract to buy and redevelop the property, had asked for and received more time again. Asbestos, arsenic, and "forever" pollution were slowing the project, and the buyer had been ready to walk away. Gulfshore Business has described the plan for that site as residences, offices, and a hotel. The mayor hopes it will also include a grocery store, retail, and restaurants.
Steven Weathers, the city's economic development director, told Florida Weekly how he will measure progress. He named redevelopment of the News-Press site, movement on City of Palms, redevelopment of the Yacht Basin, and a finished police station. He also suggested that some existing small businesses might consider "first mover advantage" while the district is changing. For anyone driving Broadway or Central between now and late 2027, the AtkinsRealis email list is the most reliable way to know which block is closed next.
If you own property in or near Midtown Fort Myers and want to understand how the Phase 1 timeline and the stadium-site decisions could affect your plans, Mitchell Properties & Salty Hook Homes can walk you through what has been approved, what is still being proposed, and what to watch for at upcoming council meetings. Schedule a Consultation and we'll go through it block by block with you.